Client:
Conamar Building Services
Location:
London
Value:
£140,000
Programme:
42 Weeks

The project included the demolition of the existing pavilion and small buildings and the construction of a new pavilion in its place.
The scope of works called for the design, co-ordination, supply, installation, test and commissioning of a complete and fully functional electric and data system.
Working closely with the design team, the look was to be minimalistic, with only specialist timber internal walls and ceilings on show where possible.
Ground floor included washrooms, toilets, changing rooms, a medical room and office.
On the top floor, a club house and kitchen were installed for guests.

Electrical installation:

Delivery of new utility services to the site.
Lighting, emergency lighting and feature lighting including the external LED street lighting.
Complete small power and distribution installation.
Kitchen and preparation room.
Fire alarm.
CCTV and security.
Data installation.
TV network installation.
Disabled alarm.
Lighting protection.
Test and commissioning of services.