LED Lighting Energy Saving Initiative, Distribution Centre Newcastle

Client: Newcastle
Location: John Lewis and Partners
Value: £80,000
Programme: 6 weeks

This energy saving initiative involved the complete replacement of all the internal and external lighting for new LED lighting. MJ Electrical Services acting as principle contractor managed the asbestos surveys and removals where required. Power data monitoring was logged before and after the installation to confirm energy saving calculations.

Careful planning and coordination with the John Lewis management team was required to avoid disruption to the distribution centres operations.